Transformer box in a power plant

News

Malaysia's BESS Push: What the MyBeST Tender and New SELCO Rules Mean for Solar Owners

April 22, 2026
|
Sarah Mei Ling

Battery storage has moved from a policy aspiration to a construction reality in Malaysia. With Tenaga Nasional Berhad's (TNB) pilot Battery Energy Storage System (BESS) project in active construction and the Energy Commission's MyBeST open tender awaiting Finance Ministry sign-off, 2026 is shaping up as the year Malaysia's grid finally gets serious about storage.

What the MyBeST Tender Actually Covers

The Malaysia Battery Energy Storage Technology (MyBeST) programme is the federal government's first open bidding exercise for utility-scale BESS. It targets 400 MW of power capacity paired with 1,600 MWh of storage, structured as four 100 MW / 400 MWh projects. According to The Edge Malaysia, the Energy Commission has completed its evaluation of submitted bids and the results are pending approval from the Finance Ministry before announcement.

Separately, TNB's own pilot BESS project is already in construction and is expected to begin operations by end-2026, Dewan Rakyat was told in December 2025. The pilot must meet NFPA 855 fire safety standards and comply with IEC 62619 and UL 9540 to satisfy the Fire and Rescue Department's requirements.

The significance of these two tracks running in parallel is not administrative overlap. It reflects Malaysia's attempt to build both regulated utility capacity and a competitive procurement model at the same time, giving the grid stability headroom as solar penetration climbs.

Sabah Already Has Southeast Asia's Largest BESS

Before the peninsular pipeline even breaks ground, Sabah has already commissioned what is described as the largest energy storage facility in Southeast Asia. Sarawak Energy inaugurated a 60 MW / 82 MWh BESS at the soon-to-be-retired Sejingkat coal-fired power plant site in early 2025. The system, first energised in December 2024, will store renewable energy and balance the grid as the coal plant is phased out.

In Sabah, a separate project tells an even larger story. A consortium led by Founder Energy is building a 310 MWp ground-mounted solar plant paired with a 620 MWh BESS, while Sabah Electricity's BESS Lahad Datu project, worth RM645 million, was contracted to Sungrow via MSR-Green Energy. Sabah's overall plan calls for 120 MW of BESS installed between 2023 and 2026, alongside grid upgrades and cross-border interconnection studies with Sarawak.

What the New SELCO Rules Change for Commercial Solar Owners

The regulatory shift that matters most for businesses already running rooftop solar sits inside the revised SELCO Guidelines released by the Energy Commission in late December 2025. Under the updated rules, the requirement to install a BESS now applies only to systems exceeding 1 MWac, replacing the previous threshold of 72 kWp.

That change removes a significant compliance burden from small and mid-sized commercial solar adopters who had been facing mandatory storage requirements under the old threshold. For larger installations above 1 MWac, however, BESS integration is now a regulatory fact. Procurement directors planning large rooftop or carpark canopy installations need to factor storage costs into their CAPEX models from the outset.

The Solar ATAP scheme, which replaced Net Energy Metering (NEM) on 1 January 2026, changes the export credit mechanism for non-domestic consumers. Bill credits for excess energy exported to the grid are now calculated based on the average system marginal price issued by the Single Buyer, rather than a fixed tariff. For businesses, this means export value will fluctuate with market conditions, making self-consumption (and therefore storage) a more financially predictable strategy than grid export.

The Economics Are Shifting

BloombergNEF analysis published in April 2025 found that utility-scale solar is already the cheapest source of bulk power generation in Malaysia, with a levelised cost of electricity (LCOE) ranging from USD 33 to USD 61 per MWh, compared with USD 78 to USD 89 per MWh for a combined-cycle gas turbine. The same analysis projects that a solar-plus-four-hour-battery system will become cost-competitive against a new gas plant by 2026 and against coal by 2028 in Malaysia.

By 2030, BNEF estimates the LCOE of solar-plus-storage will fall to USD 48 to USD 90 per MWh, driven by declining solar module and lithium-ion battery costs. For a sustainability officer building a 10-year energy strategy, that trajectory has direct implications for how soon a BESS investment can be justified on a standalone basis, separate from any regulatory compliance driver.

Grid Stability Is the Underlying Driver

Ember's research published in late 2024 makes the dependency explicit: Malaysia's power consumption is projected to grow seven times between 2024 and 2030, with data centre development accounting for a significant portion of that growth. Solar power can technically meet Malaysia's daytime demand, but the non-solar hours require either dispatchable hydro or storage. Without BESS investment, grid operators face an increasingly difficult balancing act as solar penetration rises toward the government's 30% solar target by 2035.

The national deployment plan, as outlined in academic research published in ScienceDirect, calls for 100 MW of BESS capacity to be installed starting from 2030, adding 100 MW per year until 500 MW is operational by 2034. That trajectory is a floor, not a ceiling. The MyBeST awards, once finalised, will accelerate it materially.

Malaysia's BESS story is no longer theoretical. Two sovereign utilities have already energised storage projects, a national tender is pending announcement, and the revised SELCO threshold has drawn a clear line for commercial solar owners. The question for procurement and sustainability teams is not whether to engage with storage, but how quickly project economics make it optimal to act ahead of the regulatory timeline.

Sources:

Reach out to us

Call or text us
1-800-82-0078
+60 10-281 7802
Reach out through mail
hello@i2energy.my

Reach out to us

Let’s get to know each other.
Reach out.

Contact Us
Looking to initiate your transformative LSS project?
Set a date for a meeting with us!